Project No. 352 - Owl Canyon Road (CR 13 to CR 15)

STATUS REPORT
Paved two-lane rural section of Owl Canyon Road (CR 70) featuring patched asphalt, white edge lines, double yellow center lines, and metal guardrails on both shoulders. Utility poles, grassy fields, and mountain peaks frame the background.

Last Updated: October 2026


SCOPE OF WORK

Widen and reconstruct 1 mile of roadway (Owl Canyon Rd) from CR 13 to CR 15.  Improvements include:

 

 

Owl Canyon Road

  • 6 to 8 foot paved shoulders
  • culvert & structure crossing replacements
  • utility relocations
  • subgrade stabilization
  • detour route during construction using CR 72 between CR 11 and CR 15 is anticipated
  • improvements to CR 70 & CR 15 intersection are not part of this project

PURPOSE

This project is planned due to:

  • pavement rehabilitation
  • shoulder widening
  • structure widening
  • safety improvements

BUDGET

$11,000,000

PROJECT STATUS

  • project design is in progress
  • bridge construction is expected in Fall 2027
  • road improvements are anticipated in 2028

CONTACT

Devin Traff, Project Manager   
(970) 498-5731   
email Devin