STATUS REPORT
Last Updated: January 2026
SCOPE OF WORK
Replacement of existing 10-span timber bridge on CR 45E 0.2 mile West of State Highway 287. Improvements include:
- demolition of the existing bridge and replacement with a new bridge over Dale Creek.
PURPOSE
This project is planned due to:
- safety improvements
BUDGET
$ 50,000 (design)
$1,200,000 (construction)
PROJECT STATUS
- contract awarded to Timber Wolf Excavation (TWX) LLC
- construction will begin in late January 2026
- road closure planned for February 2, 2026