STATUS REPORT
Last Updated: February 2026
SCOPE OF WORK
Overlay and Americans with Disabilities Act (ADA) improvements to Soderberg Parking Area. Improvements include:
- patching failed asphalt areas
- 2" asphalt overlay
- ADA compliant concrete and vault toilet
PURPOSE
This project is planned for:
- deteriorating pavement
- ADA compliance
BUDGET
$150,000
This project is being funded by the Department of Natural Resources.
PROJECT STATUS
- design is complete
- project will be advertised in Spring, 2026
- construction is anticipated to start late spring or early summer, 2026